One Large Rock, Two Controlled Demolition Techniques

The purpose of this project was to demonstrate two different methods of breaking a large natural rock using FRAKTUREX® non-explosive demolition agent.

The rock weighed approximately 1.5 tonnes and was brought into a garage for a controlled practical demonstration. The project was divided into two stages. First, the complete rock was split into two large sections using a straight-line drilling pattern. The two sections were then fragmented into smaller, removable pieces using a different drilling layout.

The same basic drilling parameters were used during both stages. The difference was not the drill diameter or hole depth, but the arrangement of the holes and the intended demolition result.

Project Summary

Project Practical demonstration of two rock demolition techniques
Material Natural rock
Estimated weight Approx. 1.5 tonnes
Estimated rock thickness Approx. 600 mm
Drill diameter 35 mm
Hole depth Approx. 500 mm
Stage 1 Primary splitting using holes drilled in a straight line
Stage 2 Secondary fragmentation using an adapted drilling layout
Demolition method FRAKTUREX® non-explosive demolition agent
Final result The rock was first divided into two sections and then reduced into smaller removable pieces

The Objective of the Project

This project was designed to show that the final demolition result depends strongly on the selected drilling pattern. The same rock, the same 35 mm drill bit, the same approximate hole depth and the same non-explosive demolition agent were used to demonstrate two different techniques.

Stage 1 – Primary Splitting

Objective: Divide the approximately 1.5-tonne rock into two large sections.

The holes were drilled in a straight line. As FRAKTUREX® expanded, the pressure connected the holes and created one main controlled fracture through the rock.

Stage 2 – Secondary Fragmentation

Objective: Reduce the two large sections into smaller pieces suitable for easier handling and removal.

The larger section was drilled using a grid pattern, while the smaller section required only one additional hole. The drilling layout was adapted to the size of each section.

Initial Rock and Project Preparation

Before drilling began, the rock was positioned in a controlled indoor work area. Its estimated thickness was approximately 600 mm, while the planned drilling depth was approximately 500 mm.

The holes were intentionally drilled shorter than the full thickness of the rock. This prevented the drill from breaking through the bottom while still providing sufficient depth for the expansive pressure to act effectively inside the material.

IMAGE PLACEHOLDER
Initial 1.5-tonne rock before drilling

Stage 1: Primary Splitting Along a Straight Line

The purpose of the first stage was to create one controlled fracture through the centre of the rock. A series of 35 mm holes was drilled in a straight line, with the spacing selected to allow cracks to propagate from one hole to the next.

FRAKTUREX® was then mixed according to the application instructions and poured into the clean, dry holes. As the material expanded, pressure gradually developed inside the rock and connected the drilled holes into one continuous fracture line.

IMAGE PLACEHOLDER
Straight-line drilling pattern used during the primary splitting stage
IMAGE PLACEHOLDER
FRAKTUREX® being poured into the drilled holes

Primary Splitting Drilling Parameters

Drill diameter 35 mm (1 3/8")
Hole spacing Approx. 10 × drill diameter
Hole depth Approx. 500 mm
Estimated rock thickness Approx. 600 mm

Primary Splitting Technical Illustration

The following technical illustration explains the actual drilling layout used during the first stage. It shows how a straight line of holes was used to create one controlled fracture and divide the rock into two large sections.

INFOGRAPHIC PLACEHOLDER
Primary splitting of a large rock – straight-line drilling layout

Result of the Primary Split

After the expansive reaction developed through the straight drilling line, the original rock separated into two large sections. This first stage was not intended to create small fragments. Its purpose was to demonstrate how a large rock can be divided accurately along one predetermined line.

IMAGE PLACEHOLDER
Rock divided into two large sections after the primary split

Stage 2: Secondary Rock Fragmentation

The second stage demonstrated a different demolition objective. Instead of creating one main fracture, the goal was to reduce the previously separated rock sections into smaller, manageable pieces.

The same 35 mm drill diameter and approximately 500 mm hole depth were used again. However, the drilling pattern was adapted to the size of each section.

Because the right-hand section was significantly larger, it was drilled using a grid pattern. This layout created multiple controlled fractures and allowed the rock to break into several smaller pieces.

The smaller left-hand section required only one additional drilled hole. Due to its smaller remaining size, one FRAKTUREX® application was sufficient to complete the fragmentation.

IMAGE PLACEHOLDER
Grid drilling pattern on the larger section and a single hole on the smaller section
IMAGE PLACEHOLDER
FRAKTUREX® application during the secondary fragmentation stage

Why the Drilling Layout Was Different

The second stage shows why drilling patterns must be adapted to the intended result. A straight line is suitable when the goal is to produce one main split. A grid layout is more suitable when several fractures are required to reduce a large section into smaller fragments.

Method Drilling layout Intended result
Primary splitting Holes drilled in a straight line One controlled fracture dividing the rock into two large sections
Secondary fragmentation Grid drilling on the larger section and one hole in the smaller section Multiple fractures producing smaller removable pieces

Secondary Fragmentation Technical Illustration

The second illustration shows how the two previously separated rock sections were fragmented. It highlights the grid drilling layout used on the larger section and the single-hole application used on the smaller section.

INFOGRAPHIC PLACEHOLDER
Secondary rock fragmentation – grid drilling layout

Final Result

At the end of the project, the approximately 1.5-tonne rock had been completely reduced into smaller pieces. The final fragments were significantly easier to handle, move and transport than the original rock.

The project successfully demonstrated that the same non-explosive demolition agent and the same basic drilling parameters can produce very different results when the drilling layout is changed.

IMAGE PLACEHOLDER
Final top view of the fully fragmented rock

What This Project Demonstrated

  • A large rock can be divided accurately using a straight-line drilling pattern.
  • Previously split sections can be reduced further using a grid drilling pattern.
  • Smaller sections may require fewer holes than larger sections.
  • The drilling layout should always be selected according to the desired final result.
  • The same drill diameter and hole depth can be used for different demolition objectives.
  • FRAKTUREX® enables controlled rock splitting without conventional explosives.

Two Techniques, One Demolition Agent

The main lesson from this project is that successful rock demolition depends not only on the product, but also on selecting the correct drilling layout.

During the first stage, a straight line of holes created one main fracture and divided the rock into two large sections. During the second stage, a grid pattern on the larger section and one additional hole in the smaller section produced multiple fractures and completed the fragmentation process.

Together, the two stages provide a clear practical demonstration of how FRAKTUREX® can be used both for precision rock splitting and for final rock fragmentation.

Planning a Rock Splitting Project?

FRAKTUREX® provides a controlled, non-explosive solution for splitting large rocks and reducing them into manageable pieces.

Select the drilling layout according to the result you want to achieve.